1 - Survey work for milestone work Installation
2 - Civil work , excavation trench & installation electrical Fondation
3 - Pulling Cable
4 - Installation of Flood Lighting Pols
5 - Installation of Lighting and Instrument cable Trays
6 - Fabrication and installation of cable Tray supports
7 - Installation of LV Bus Duct
8 - Installation of power, control and Earthing cables.
9 - Installation of Transmitters, Gauges, Valves, DCS, PLC PT,TT etc.